Work ending 19/02/ 2016

  • Work ending 19/02/ 2016

    Work ending 19/02/ 2016

    Its been a nice but chilly week this week.
    Thats us finished the 110 metres of Pointing. We had a massive tidying effort today to to get rid of all the old cement mortar and the brushed up lime mortar that we have just put in! It amazes us every time just how much rubbish there is at the end of a cutting out and re-pointing job!

    Theres nothing much to see this week but once the scaffolding is down i will get more pictures.
    We are leaving the hessian on the wall to protect it from frost or any heavy rain.

     